In Project Management a Change Management Process is a set of repeatable, documented steps for requesting, logging, assessing, reviewing and implementing change requests. stakeholdermap.com
An example Change Management process
This is an extract of a change process from a real world programe.1. Request for change is made
Changes and issues are captured through Project Team meetings, a working group of external stakeholders including other government agencies, meetings of the Project Board, outcomes of approval stages and through monitoring by the Project Team and Project Sponsor.These forums enable changes to be captured at all levels from minor scope changes made to correct errors, to major issues arising from government policy changes. Most scope changes are captured at approval stages, but major changes to content are captured through the knowledge of policy developments that come out of the working group and from the networking carried out by the Project Sponsor and Project Board.
2. Register and assess the change
Change requests are captured on a central change log that enables monitoring of change levels by the Change Manager.Once the change is captured the change is assessed by the Project Manager using specialist advice from the Project Team. The Project Manager considers:
- Does it relate to the project?
- Is it really a risk or an issue that can be accepted or dealt without the change?
- Is it actually a new project?
- Is it required to meet the project goals & KPIs?
- What will happen if the change is not implemented?
Change Management Process flow chart
Download the Change Process chart
Download this Change Management process in Microsoft Visio
Download this Change Management process in PDF
3. Review and submit RFC to Change Board
If the change is valid the Project Manager assesses the impact of the change with the project team and submits the change via a Request for Change Form to the Change Manager. It is then submitted to the Change Board who assess the change and approve or reject it.This process interfaces with the Configuration Management Process for the project and for the programme.
The Change Manager is responsible for managing change across the programme. They spot trends, wider strategic issues, carry out audits and quality checks and work to improve the process.
4. Change Board accept or reject the change
The Change Board includes the client and senior managers who have a strategic overview of the contract. They assess whether the change is within programme tolerances and are able to approve most changes. They may look at:- the effect of the change on the business case,
- the change in relation to the programme as a whole,
- knock on effects of the change,
- any additional risks related to the change,
- any lessons that can be learnt from the change,
- any trends that change reveals.
5. Update plans & implement the change
Once the change is approved the change log is updated and stakeholders are informed. The Project Manager then works with the project team to plan the implementation of the change; amending the project and stage plans, sourcing any additional equipment or personnel, updating the configuration items and completing the work package(s).Read more on Project Management
- Project Management articles
- Project audits
- Configuration Management
- Construction Management
- Project funding
- How to Delegate - learn the fastest and most effective way to delegate
- Project methods vs tools and techniques
- Project monitoring and control
- Small business productivity
- How to smash any job interview question using STAR - a how to guide
- Project Management Triangle - Time, Cost and Quality - Iron Triangle - understand the key principle in managing successful projects
- What is programme management
- Why do we need project managers?
- Why Project Management fails