Drawing of Stakeholder map

Project Management, Project Planning, Templates and Advice

Expertly crafted, ready-to-use project schedules:

Construction Project WBS

by | reviewed 2024-04-22
This Work Breakdown Structure is for a Construction project. It represents the first step in scheduling, which is to breakdown the work. This example separates the work into logical areas or Work Packages. It includes site preparation, ground beams, flooring, brickwork, electricity, plumbing and finishes.
To see the entire WBS download the visio or PDF.
work breakdown for a construction project

1 Construction Work Breakdown structure text version

1.2 Site prep

  • 1.2.1 Mobilisation

  • 1.2.2 Excavation

  • 1.2.3 Piling

1.3 Pile Caps/Ground Beams

  • 1.3.1 Cut-off Piles and Blinding

  • 1.3.2 Formwork & rebar

  • 1.3.3 Concrete

1.4 Structural Steel

  • 1.4.1 Erect Steel Frame

  • 1.4.2 Holorib Floors

1.5 External

  • 1.5.1 Cladding

  • 1.5.2 Roofing

1.6 Floor Slab

  • 1.6.1 Sub-base & Blinding

  • 1.6.2 Formwork & Concrete

1.7 Brickwork

  • 1.7.1 External Brickwork

  • 1.7.2 Internal Brickwork

1.8 M & E Services

  • 1.8.1 Plumbing

  • 1.8.2 Electric

1.9 Finishes

  • 1.9.1 Joinery

  • 1.9.2 Plastering

  • 1.9.3 Decorating

Download this Construction Project WBS

Visio diagram of the Construction work breakdown structure

PDF version of the Construction WBS