Drawing of Stakeholder map

Project Management, Project Planning, Templates and Advice

  • Concise, focused guide that cuts through the clutter
  • Step-by-step instructions for creating a project plan in under a day
  • Master essential skills like work breakdowns and task sequencing
  • Real-world troubleshooting for 20 common scheduling challenges
  • Rapidly get up to speed if you're new to Microsoft Project
  • Includes glossary, support resources, and sample plans
The cover of the book 'Essential Microsoft Project: The 20% You Need to Know'

What is the Critical Path Method?

by | reviewed 2023-08-19
Critical Path Method (CPM)
A schedule network analysis technique used to determine the amount of scheduling flexibility (the least amount of float) on various logical network paths in the project schedule network, and to determine the minimum total project duration. Early start and finish date are calculated by means of a forward pass using a specified start date. Late start and finish dates are calculated by means of a backward pass, starting from a specified completion date, which sometimes is the project early finish date determined during the forward pass calculation.
See also Critical Path, Critical Path Analysis and What is a Network Diagram?
Meaning and definition of Critical Path Method

 