What is Actual Cost of Work Performed?
Actual Cost of Work Performed (ACWP)
Total cost actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component.
In earned value management, ACWP is also called Actual Cost (AC). You can report it for one period, such as this month, or as a cumulative total from the start of the project. A task can still be in progress and have actual costs. [1] [2]
Watch the actual costs add up
Two desks are finished. Watch labour, materials and equipment build the actual cost total, then see why £1,200 of costs means a £200 overrun on this work.
Open the animation on its own. The figures and explanation are also set out below.
How to calculate ACWP: a worked example
Your office refit includes building five identical desks. Each has an agreed budget of £500, giving a total budget of £2,500. By Friday, two desks are finished and the other three have not started.
The following costs have been incurred for the two completed desks. These are all the costs charged to the work in this simple example.
| Cost | Calculation or record | Actual cost |
|---|---|---|
| Labour | 20 hours at £35 per hour | £700 |
| Materials | Materials used for the two desks | £400 |
| Equipment | Equipment hire used for this work | £100 |
| Actual Cost of Work Performed | £1,200 | |
ACWP = actual labour + actual materials + other actual costs
£700 + £400 + £100 = £1,200
Use actual cost records to calculate ACWP. Multiplying the total budget by the percentage complete calculates earned value under a suitable progress method; it does not tell you the actual cost.
ACWP, earned value and planned value: what is the difference?
These measures answer different questions. Suppose the plan called for three desks to be finished by Friday, but only two are complete. [3]
| Measure | Question it answers | Desk example |
|---|---|---|
| Actual cost ACWP / AC | What did the work done actually cost? | Recorded costs: £1,200 |
| Earned value BCWP / EV | What was the budgeted value of the work done? | 2 completed desks × £500: £1,000 |
| Planned value BCWS / PV | What was the budgeted value of the work due by now? | 3 planned desks × £500: £1,500 |
Lower spending can hide a problem. The £1,200 actual cost is below the £1,500 planned value. That might look encouraging, but the team has delivered only £1,000 of budgeted work. The completed work is over budget, and one desk behind the plan.
Is the work over budget?
Compare ACWP with the earned value of the same work. Cost variance is earned value minus actual cost. A negative answer means the work cost more than budgeted. [4]
Cost variance (CV) = EV − AC
£1,000 − £1,200 = −£200
The two completed desks cost £200 more than their £1,000 budget. The final project cost still depends on how the remaining work goes.
You can also calculate the Cost Performance Index (CPI): £1,000 ÷ £1,200 = 0.83. That means about 83p of budgeted work has been earned for each £1 of actual cost. A CPI below 1 signals poor cost performance. [5]
Which costs belong in ACWP?
Include the costs incurred for the work being measured. Depending on the project, this can mean labour, materials, subcontractors, equipment and allocated indirect costs. Use the same cost categories as the budget so the comparison is fair. [6]
- Match the reporting date. Compare Friday's earned value with costs through Friday, rather than with next week's costs.
- Account for work already received. If the work has been done but an invoice is late, use your approved accrual or estimated-actuals process. Reconcile it when the invoice arrives so the cost is counted once.
- Keep future work separate. A purchase order for work still to be done is a commitment. It does not automatically become ACWP when the order is placed.
- Label period totals clearly. “This month's ACWP” and “ACWP to date” are different figures. Use the same period for the earned value comparison.
The payment date alone does not settle when a cost belongs in ACWP. What matters is recognising the cost of the work performed under the project's cost-accounting rules. [1] [6]
ACWP in Microsoft Project
In Microsoft Project desktop, the ACWP field shows actual costs for work done up to the status date, or today's date. Its calculation depends on actual work, resource rates, fixed costs and cost accrual settings. [7]
- Set the status date for your report.
- Check that progress, actual work and cost information are up to date.
- Add the ACWP, BCWP and CV fields to your task view.
- Read them together. BCWP needs a saved baseline and progress information to provide an earned value comparison.
Project can calculate actual costs from the information you enter. Check those figures against your cost records, particularly when invoices, rates or fixed-cost timings have changed.
Related project management terms
Sources
- U.S. Department of Defense: EVM definitions, including ACWP and estimated actuals.
- Microsoft: earned value analysis, for the rest of us.
- U.S. Department of Energy: earned value management.
- Microsoft: CV fields.
- Microsoft: CPI fields.
- U.S. Department of Energy: integrated project management using the earned value management system, section 6.2.11 on accumulating costs.
- Microsoft: ACWP fields; BCWP fields.
The desk example and animation are illustrative.