Who can approve the change? Who will deliver it? Who needs to be involved before the decision is made?
A change management RACI puts those responsibilities in one place. Download the free Excel template in light or dark, then use the dropdowns and assignment checks to build a matrix your team can agree on.
The worked example follows a change request from logging and assessment through approval and implementation.
Download your change management RACI template
Both versions contain the same tasks, worked example, dropdowns and formulas. Choose the appearance you prefer.
Light Excel template
A white background with navy headings, pale input cells and coloured RACI assignments.
Download light template (.xlsx)Dark Excel template
A charcoal background with bright text, highlighted input cells and distinct role colours.
Download dark template (.xlsx)Prefer a reference copy? Download the PDF example.
What is included?
| Worksheet | What you can do |
|---|---|
| Your RACI | Start with ten suggested change management tasks and ten spare rows. Rename the six role columns and add the people or teams filling them. |
| Worked example | See a completed matrix covering assessment, approval, communication, plan updates and implementation. |
| Guide & resources | Follow the setup steps, look up each code and understand the messages in the assignment check column. |
The workbook also includes project details, a review date, a version field and a preparer field. Frozen headings keep the tasks and role names in view as you scroll.
What do the RACI roles mean?
Use the letters to show each role's involvement in a task or decision.
- R: Responsible
- Does the work. More than one role can be responsible when a task needs several contributors.
- A: Accountable
- Owns the outcome. Give each task one accountable role so there is a clear point of ownership.
- C: Consulted
- Provides advice or input before the task or decision is completed.
- I: Informed
- Receives updates about progress or the outcome.
- R/A: Combined
- The same role does the work and owns the outcome. The template counts this as both R and A.
Leave a cell blank when that role has no involvement. For more detail, see how to use and create RACI charts.
Change management RACI example
This example uses six roles: project manager, project team, programme manager, project sponsor, change manager and Change Approval Board (CAB). It gives the board responsibility for approving or rejecting the request.
Read across a row to see who is involved in a task. On a small screen, scroll the table sideways to see all six roles.
| Task / decision | Project manager | Project team | Programme manager | Project sponsor | Change manager | Change Approval Board |
|---|---|---|---|---|---|---|
| 1. Register the change in the change log | A | I | No involvement | I | R | No involvement |
| 2. Assess the change | R/A | C | I | I | C | No involvement |
| 3. Tell the requester the assessment outcome | R/A | I | No involvement | C | I | No involvement |
| 4. Submit the change to the Change Approval Board (CAB) | I | I | C | C | R/A | No involvement |
| 5. Review and approve or reject the change | I | No involvement | I | C | C | R/A |
| 6. Tell stakeholders the CAB decision | C | I | No involvement | A | R | No involvement |
| 7. Update project plans, the risk register and issue log | R | C | No involvement | A | No involvement | No involvement |
| 8. Update the change log | A | I | I | I | R | I |
| 9. Update programme plans | C | No involvement | R/A | I | No involvement | No involvement |
| 10. Implement the change | A | R | C | C | I | I |
Read one row: assessing the change
The project manager has R/A for the assessment. The project team and change manager are consulted for their input. The programme manager and sponsor are informed. Approval is a separate task, owned by the board in row five.
Match the role assignments to your own change management process. For a larger change, add tasks for testing, staff communication, training, handover or reviewing the outcome.
How to use the change management RACI template
- Define the change. Open Your RACI and enter the project or change name, review date, version and preparer.
- Name the roles. Rename the six role headings to match your team. Add a named person or team above each heading.
- Check the task list. Keep the suggested tasks that apply, rewrite any that need more detail, and use the spare rows for missing tasks or decisions.
- Choose the codes. Use the dropdowns to select R, A, C, I or R/A. Give each task one A and at least one R.
- Resolve the checks. Use the message at the end of each row to find gaps, duplicate accountability or invalid codes.
- Agree and review. Discuss the assignments with the people involved. Update the matrix when responsibilities, scope or approval arrangements change.
Understand the automatic assignment checks
The final column tells you what needs attention. The count above it shows how many rows need review.
| Message | What to do |
|---|---|
| Add R / Add A | Add the missing responsible or accountable role. Add R and A means both are missing. |
| One A only | Choose one accountable role. Change the other assignments to reflect their actual involvement. |
| One A; add R | Remove the extra accountable roles and assign someone to do the work. |
| Check code | Use the dropdown values. Check pasted entries for unfamiliar codes or extra spaces. |
| Add task | Add a task description, or clear the role assignments from an unused row. |
| Assigned | The row has valid codes, exactly one accountable role and at least one responsible role. This describes the assignments, not delivery progress. |
For example, entering R/A for the project manager and A for the sponsor gives the row two accountable roles. The check will ask you to choose one.
Review the responsibilities with your team
A row can satisfy the formula and still need a conversation. Before agreeing the matrix, ask:
- Does the accountable role have the authority to decide? An approval task needs an owner who can make that approval.
- Is the work shared sensibly? Read down each role's column. A long list of Rs may reveal a workload problem.
- Are the consulted people needed before the decision? If they only need the outcome, I may be more appropriate.
- Is someone named behind each group? A label such as “project team” is more useful when everyone knows who will coordinate the work.
Common questions
Can the same person be responsible and accountable?
Yes. Choose R/A when the same role does the work and owns the outcome. It satisfies both checks without creating a second accountable role.
Do I need to complete every cell?
No. Leave cells blank where a role has no involvement. Each task still needs one A and at least one R.
Can I add more tasks?
There are 20 prepared rows. To add more, insert a row inside the matrix and copy a prepared row's formulas, dropdowns and formatting.
Are the light and dark versions different templates?
They have the same worksheets, role codes, example and checks. Only the appearance changes.
Related templates and guides
General RACI template
Assign roles across a project or business process.
How to create a RACI chart
Understand the roles and build a useful responsibility matrix.
Change management process
Connect the responsibilities to the steps in managing a change request.
What is change management?
Explore the wider work of helping an organisation make a change.
Download your free RACI template