Drawing of Stakeholder map

Microsoft Project, Project planning, Templates and Advice

  • Concise, focused guide that cuts through the clutter
  • Step-by-step instructions for creating a project plan in under a day
  • Master essential skills like work breakdowns and task sequencing
  • Real-world troubleshooting for 20 common scheduling challenges
  • Rapidly get up to speed if you're new to Microsoft Project
  • Includes glossary, support resources, and sample plans
The cover of the book 'Essential Microsoft Project: The 20% You Need to Know'

Shed project plan - Microsoft Project download

Planning a shed build? This downloadable Microsoft Project plan lays out every step needed to take your shed from idea to completion. Whether you're a seasoned project manager or simply want a clear, structured approach, this schedule offers a practical example of how to manage a small construction project using Microsoft Project. It follows a logical progression—from early design and site prep through to construction, finishing, and final inspection.

This plan is featured in the book Essential Microsoft Project: The 20% You Need to Know, which focuses on using Microsoft Project efficiently and effectively. If you're learning how to use the software or want to see a real-world application, this example provides a complete yet concise breakdown of tasks, durations, dependencies, and assigned resources—all designed to be immediately usable or easily customized for your own shed project.

Contents of this plan

Task Name Duration Start Finish Predecessors Resource Names
shed-project-schedule 17.75 days Fri 03/05/24 Tue 28/05/24
   Design and Planning 8.5 days Fri 03/05/24 Wed 15/05/24
      Sketch preliminary design. 1 day Fri 03/05/24 Fri 03/05/24 Designer
      Finalize design and blueprint. 2 days Mon 06/05/24 Tue 07/05/24 2 Designer
      List materials and tools needed. 0.5 days Wed 08/05/24 Wed 08/05/24 3 Builder
      Obtain necessary permits. 5 days Wed 08/05/24 Wed 15/05/24 4 Client
   Site Preparation 9.5 days Mon 06/05/24 Fri 17/05/24
      Choose a suitable location. 0.25 days Mon 06/05/24 Mon 06/05/24 2 Client
      Clear and level the site. 1.5 days Wed 15/05/24 Thu 16/05/24 7,5 Builder
      Mark foundation boundaries. 0.5 days Fri 17/05/24 Fri 17/05/24 8 Builder
   Foundation Construction 3 days Fri 17/05/24 Wed 22/05/24
      Dig the foundations. 2 days Fri 17/05/24 Tue 21/05/24 9 Builder
      Pour concrete or lay paving slabs. 1 day Tue 21/05/24 Wed 22/05/24 11 Builder
   Frame Construction 1 day Wed 22/05/24 Thu 23/05/24
      Set up the floor frame. 0.5 days Wed 22/05/24 Wed 22/05/24 12 Builder
Construct wall frames. 0.25 days Thu 23/05/24 Thu 23/05/24 14 Builder
Install windows and doors. 0.25 days Thu 23/05/24 Thu 23/05/24 15 Builder
Roofing 1 day Thu 23/05/24 Fri 24/05/24
Install roof trusses or rafters. 0.5 days Thu 23/05/24 Thu 23/05/24 16 Builder
Lay roofing material (e.g., shingles). 0.5 days Fri 24/05/24 Fri 24/05/24 18 Builder
Finishing and Painting 1.75 days Fri 24/05/24 Tue 28/05/24
      Install siding or exterior cladding. 0.25 days Fri 24/05/24 Fri 24/05/24 19 Builder
      Paint or stain the shed. 0.5 days Fri 24/05/24 Mon 27/05/24 21 Client
      Set up interior (shelving, hooks, etc.). 1 day Mon 27/05/24 Tue 28/05/24 22 Client
   Final Inspection 0.5 days Tue 28/05/24 Tue 28/05/24
      Review construction for any missed steps or errors. 0.5 days Tue 28/05/24 Tue 28/05/24 22FS+1 day Designer
      Ensure the shed is waterproof and structurally sound. 0.5 days Tue 28/05/24 Tue 28/05/24 22FS+1 day Builder
      Approve completion and sign-off invoices 0 days Tue 28/05/24 Tue 28/05/24 25,26,23 Client