Project Management Triangle

Learn to explain project trade-offs and agree what can change when everything feels fixed.

A real project dilemma

The date is fixed.
The work won’t fit.

The conference materials won’t be ready in time. What would you change?

See how I solved it
Time, cost and quality: the conference date is fixed A project triangle connects time, cost and quality. Time is fixed by the conference date. A question mark invites you to consider what can change. Time DATE FIXED Cost Quality ?
One constraint is fixed. What can move?

One of the first project management concepts that I learned was the time, cost, quality triangle. I was given the task of managing a conference and I was trying to find a way to express a common challenge. The conference date was fixed. There simply weren't enough days to write, design and print the completed full-colour training materials.

The Triangle of Objectives

project triangle, original by Dr Martin Barnes

In the mid 1980s Dr Martin Barnes created the Triangle of Objectives. The triangle demonstrates that quality cost and time are interrelated. Focussing or fixing one point of the triangle impacts the other two (Lock, 2007, p21).

How I solved the conference problem

In the case of the conference a trade off had to be made in quality or cost to meet the fixed date. In the end the printing was changed from colour to black and white and drafts were sent to the first day with final versions arriving on the third day.

Dr Barnes later updated the triangle to performance, cost and time as he felt that quality implied little more than compliance with specifications.

Dennis Lock points out that many more deriviations of the triangle have since been developed (2007, p22). My perception is that the most often seen variation is to replace performance or quality with scope . In my opinion this is a calculated attempt to insist that compliance to spec is - as Barnes tried to avoid - all that is required. This is perhaps partly the cause of common complaints that waterfall methods are inflexible, assume fixed requirements and are resistant to change.

Common variations of the project triangle

Project triangle with scope, cost and time around quality at the centre
This version places quality in the centre, making a clear distinction between scope and quality. Here scope is the deliverables and specification, but quality has moved to centre, so that any change to any side affects quality (office.microsoft.com, 2014).
Kliem and Ludin version of the triangle of objectives
Kliem and Ludin modified the triangle of objectives to show people at the centre. They called this The Four Variables of Project Success.
if people are not considered a crucial element, the project will fail, even in the presence of good plans, organizational structure, and proper controls (Kliem, Ludin and Robertson, 1997, p24).
Dennis Lock version of the triangle of objectives, using specification rather than quality
Lock proposed a combined version of Barnes's original with Kliem and Ludin's, but replaced 'quality' with 'level of specification'. Arguing that if quality is defined as 'fit for purpose' it can never be negotiable. 'Performance' or 'Level of specification is more appropriate because that can be negotiated (Lock, 2007, p22).

How to use the triangle

Decide at the start of a project which version of the triangle you will use and agree with the project sponsor which of the three or four objectives are most important. Assess changes, risks and issues against the triangle and weigh up your course of action against the impact on the critical objective.

Project Management Triangles

1 / 5

Digging by hand

Digging foundations by hand takes 2 days

Using an excavator

Digging foundations with an excavator will shorten the duration to 1 day.

Cost is fixed

Reject the change requests as it will increase the cost of the project.

The change could be considered in a future phase.

REJECT

Time is fixed

Reject the change request as it will delay your project end date.

REJECT

Quality is fixed

The widget must meet the agreed quality standards. Do not make room for it by cutting essential testing, security, accessibility or reliability.

Assess the time and resources needed to build and test it properly. If time and cost can change, seek approval for a revised plan. If they cannot, agree a scope exchange or defer the widget.

ACCEPT ONLY WITH A PLAN THAT PROTECTS QUALITY

Fixed quality does not automatically mean rejecting the change. It means the delivered product must still meet its agreed requirements.

Try the Iron Triangle Explorer

Put the ideas into practice with an interactive CRM project. Change the team and first-release features to explore the effects on time and cost.

Open the interactive Iron Triangle Explorer

Note on the history of the triangle

According to Andy Oppel some claim that the concept of three interelated objectives comes from Hollywood where producers manage the interelated objectives/aspiration of a quality film, produced quickly on small budget (2009).

Project triangle references

Office, 2014, The project triangle , [online] Available at: http://office.microsoft.com/en-gb/project-help/the-project-triangle-HA010351692.aspx [Accessed 19 Novemeber 2014]

Andy Oppel, 2009. Data Modeling , McGraw-Hill.

Ralph L. Kliem, Irwin S. Ludin, Ken L. Robertson, 1997. Project Management Methodology: A Practical Guide for the Next Millenium , New York:CRC Press.

Dennis Lock, 2007. Project Management , 9th ed. Aldershot:Gower Publishing Limited.