Drawing of Stakeholder map

Project Management, Project Planning, Templates and Advice

Expertly crafted, ready-to-use project schedules:

What is a Claim in Project Management?

by | reviewed 19/06/2024

A claim, in the context of project management, refers to a request, demand, or assertion of rights made by one party (usually a seller) against another party (usually a buyer) for consideration, compensation, or payment under the terms of a legally binding contract. Claims often arise due to disputed changes or disagreements over the interpretation of contract terms.

What is a Claim?

A claim can be seen as a formal request for additional compensation or time extension based on the occurrence of specific events or conditions that impact the project's original scope, schedule, or cost. These events may include unforeseen site conditions, changes in project requirements, delays caused by one party, or other factors that were not anticipated when the contract was signed.

Why Are Claims Important?

Claims play a crucial role in project management as they help to ensure that all parties are fairly compensated for any extra work or costs incurred beyond the original contract terms. Proper management of claims can prevent disputes from escalating into legal battles, which can be costly and time-consuming. Furthermore, effectively handling claims contributes to maintaining good relationships between parties and ensures project continuity.

How to Handle Claims

Managing claims involves several steps, each of which must be handled meticulously to ensure a fair resolution:

  1. Identify the Claim: Recognize the potential claim as early as possible. Documentation of the issue is key.
  2. Notify the Other Party: Inform the other party of the claim in writing. Include all relevant details and supporting documents.
  3. Document the Claim: Collect all necessary documentation to support the claim. This may include photographs, correspondence, logs, and any other relevant records.
  4. Submit the Claim: Formally submit the claim to the other party. Ensure that the submission complies with the contract's specified procedures.
  5. Negotiate and Resolve: Engage in discussions with the other party to resolve the claim. Aim for a fair settlement that avoids further escalation.
  6. Follow-Up: Once the claim is resolved, document the outcome and ensure that any agreed-upon actions are implemented.

When to Use Claims

Claims should be considered whenever there is a legitimate deviation from the original contract terms that impacts the project's scope, cost, or schedule. Common scenarios that may give rise to claims include:

  • Unforeseen site conditions
  • Design changes or errors
  • Delays caused by the client or other contractors
  • Regulatory changes
  • Force majeure events

Best Practices for Managing Claims

To effectively manage claims, consider the following best practices:

  • Maintain Clear Documentation: Keep detailed records of all project activities, communications, and changes.
  • Understand the Contract: Have a thorough understanding of the contract terms and conditions to identify potential claim scenarios.
  • Communicate Proactively: Maintain open and transparent communication with all parties involved to prevent misunderstandings.
  • Act Promptly: Address potential claims as soon as they arise to prevent escalation.
  • Seek Expert Advice: Consult with legal or claims experts to navigate complex claim situations effectively.

Things to Avoid

When managing claims, it is essential to avoid the following pitfalls:

  • Ignoring Potential Claims: Failing to address issues promptly can lead to more significant problems down the line.
  • Lack of Documentation: Without proper documentation, it is challenging to support a claim.
  • Poor Communication: Miscommunication can exacerbate disputes and hinder resolution efforts.
  • Delaying Action: Procrastination can weaken your position and reduce the chances of a favorable outcome.
  • Being Unreasonable: Aim for a fair resolution rather than an unrealistic demand, which can damage relationships.

Pros and Cons of Claims

Understanding the advantages and disadvantages of pursuing claims can help in making informed decisions:

Pros

  • Ensures fair compensation for additional work or costs
  • Helps maintain project profitability
  • Encourages accountability and adherence to contract terms
  • Can lead to improved project outcomes through early issue resolution

Cons

  • Can be time-consuming and costly to resolve
  • May strain relationships between parties
  • Potential for disputes to escalate into legal battles
  • Requires thorough documentation and adherence to procedural requirements

Real-World Examples of Claims Made on Construction Projects

Balfour Beatty Regional Construction Limited v Van Elle Ltd [2021] EWHC 794 (TCC)

In a case reviewed by the Technology and Construction Court in March 2021, Balfour Beatty Regional Construction Limited (“Balfour Beatty”) v Van Elle Ltd (“Van Elle”), it was determined that a subcontract covered work done by a subcontractor even though it was unsigned when the work commenced.

Background

Balfour Beatty, the main contractor, was tasked with designing and constructing a sub-sea cable manufacturing facility in Newcastle upon Tyne. Van Elle was subcontracted for foundational piling work, including a specific section called the “Northern Carousel.” Van Elle began work before a formal subcontract was signed. After installation, significant settlement issues were discovered, necessitating extensive remedial work. Balfour Beatty sought to recover these costs from Van Elle and requested indemnity for any liability to the employer.

Van Elle argued that the work on the Northern Carousel was governed by an earlier quotation incorporating its standard terms, which included liability limitations, rather than the unsigned formal subcontract.

What Did the Court Decide?

The court concluded that the formal subcontract applied to all works, including those performed before it was signed. Additionally, the Judge commented on the limitations Van Elle included in their standard terms, although these comments were not binding.

Takeaway

This case highlights the importance of defining the terms of work at the beginning of a project and ensuring standard terms are reviewed in light of judicial interpretations regarding liability limitations.

JSM Construction Limited v Western Power Distribution (West Midlands) plc [2020] EWHC 3583 (TCC)

In this case, the Technology and Construction Court considered the adequacy of payment provisions in a construction contract that lacked a final account mechanism.

What is a Final Account?

Final accounts in construction projects are prepared at the completion phase to determine the final payment due to the contractor, including all necessary adjustments.

Background

JSM Construction Ltd (“JSM”), a utilities service provider, entered into a contract with Western Power Distribution (West Midlands) plc (“Western Power”) to install cables and ductwork in Birmingham. The contract provided for interim payments but did not include a final account provision.

After submitting several interim applications, JSM made a final application based on a remeasurement of the work. Western Power refused to pay, arguing that JSM was only entitled to interim payments and not a final account. JSM commenced court action, claiming the contract’s payment mechanisms were inadequate and that final account provisions from the Scheme for Construction Contracts 1998 should be implied.

What Did the Court Decide?

The Judge held that section 110 of the Construction & Regeneration Act 1996 did not require a separate final account procedure for a payment mechanism to be adequate. Western Power’s application to strike out JSM’s claim failed, as the Judge needed to consider the full facts.

Takeaway

A lack of a final account mechanism in a construction contract does not necessarily mean one will be implied. Parties should not rely on statutory remedies to address inadequate contract terms.

These real-world examples illustrate the complexities and nuances of claims in construction projects, highlighting the importance of clear contractual terms and thorough documentation. Understanding and effectively managing claims can help prevent costly disputes and ensure fair compensation for all parties involved.

Real-World Examples of Claims Made on IT Projects

CIS General Insurance Limited v IBM United Kingdom Limited [2021] EWHC 350 (TCC)

In this case, the High Court examined a dispute between CIS General Insurance Limited (CIS) and IBM United Kingdom Limited (IBM) over a failed IT project contract, resulting in claims for wasted expenditure and damages due to the contract's termination.

Background

CIS entered into a 10-year contract with IBM for the supply and management of a new IT system for its insurance business, with the platform scheduled for delivery by 31 December 2017. This deadline was crucial as CIS's insurance business was to be separated from the Co-op Bank. However, the project encountered significant delays.

IBM submitted an invoice (AG5) to CIS for nearly £2.9 million, claiming it was for software licences as part of a contract milestone. CIS refused to pay, asserting that the AG5 milestone was not met and they had neither authorized the payment nor issued a purchase order for it.

CIS informed IBM of its intent to set off the invoice amount against any sums due. IBM issued a final notice for the invoice, which CIS again refused to pay. Subsequently, IBM attempted to terminate the contract based on CIS’s non-payment. CIS contested this termination, viewing it as a repudiatory breach, which they accepted.

What Did the Court Decide?

The court ruled that:

  • IBM was not entitled to terminate the contract based on CIS's failure to pay the AG5 invoice.
  • IBM's attempted termination constituted a repudiatory breach, which CIS accepted.
  • IBM breached the contract due to delays and inadequate reporting on those delays.
  • CIS’s primary claim for £130 million in wasted expenditure was excluded by the contract.
  • CIS was awarded nearly £16 million for pre-termination breaches.
  • IBM could set off the nearly £2.9 million AG5 invoice against the amount owed to CIS.

Takeaway

This case highlights the importance of clearly defined milestones, payment authorizations, and the implications of contract termination rights. It underscores the necessity for meticulous contract management and the potential complexities involved in IT project disputes. Accurate reporting and adherence to contractual obligations are crucial in avoiding significant financial and legal consequences.

BSkyB v EDS [2010] EWHC 86 (TCC)

Background

In 2001, Electronic Data Systems (EDS) agreed to provide a Customer Management System to British Sky Broadcasting (BSkyB). However, the system failed to function as required, prompting BSkyB to sue EDS. BSkyB claimed that EDS made negligent and fraudulent representations during negotiations, specifically regarding their ability to complete the project within the stated timeframe. A key issue was a fraudulent misrepresentation by EDS salespeople, which convinced BSkyB to enter into the contract. In legal terms, misrepresentation occurs when a false statement of fact, rather than opinion, induces a party to enter a contract, and it can be made either verbally or in writing.

IT contracts often include limitations of liability. In this case, EDS attempted to limit its liability to $30 million. However, if BSkyB could prove fraudulent misrepresentation, this limitation would not apply, as liability for fraud cannot be limited. The court found that EDS had indeed made negligent and fraudulent misrepresentations, allowing BSkyB to claim all damages caused by these misrepresentations without any limit.

What Did the Court Decide?

The court ruled that:

  • EDS had made negligent and fraudulent misrepresentations.
  • BSkyB was entitled to claim damages without any limitation due to the fraudulent nature of EDS’s misrepresentations.

Why is the Case So Important?

This case is pivotal as it demonstrates how a customer can bypass a supplier's limitations of liability. Limitations of liability are crucial in IT contracts due to the potentially high consequences of system failures. Here, the claim's value (£700 million) vastly exceeded both the amount paid (£48 million) and the agreed liability limit ($30 million). This precedent encourages dissatisfied buyers of large IT systems to challenge suppliers, even if liability limitations are contractually stipulated.

The case also highlights the high costs and extended duration of English litigation. The total estimated costs for EDS were around £70 million, significantly higher than the system's cost. The litigation involved reviewing 500,000 documents, 70 witnesses, and nearly a year of court time. The case started in 2002, and the judgment was delivered in January 2010, 18 months after the trial concluded. The judgment itself was 468 pages long. While the original claim was £700 million, the actual damages awarded were around £220 million, with significant legal costs.

Final Comments

One contributing factor to the high costs was the nature of the dispute, which revolved around "who said what to whom and when." The credibility of witnesses was critical, especially since BSkyB alleged fraud. A notable moment was when EDS’s managing director, Joe Galloway, claimed to have an MBA from Concordia College, which turned out to be purchased online. This was dramatically proven in court when counsel bought a similar degree for his dog.

During the litigation, EDS was acquired by Hewlett Packard in 2008.

These real-world examples of IT project claims illustrate the intricate and often challenging nature of contract management and dispute resolution in the technology sector. The cases of CIS General Insurance Limited v IBM United Kingdom Limited and BSkyB v EDS underscore the necessity for clearly defined contract terms, including milestones, payment authorizations, and termination rights, to avoid significant disputes and costly litigation. They highlight the severe consequences of misrepresentation during negotiations, the potential to bypass contractual limitations of liability in cases of fraud, and the importance of effective project management and accurate reporting.